Brent Wahl, the CFO of NextDecade, has resigned to take up a role at an unnamed digital infrastructure company. His last day will be October 20th, though he will enter a consulting agreement with the company through the rest of the year.
Mike Mott, Senior VP, Enterprise Transformation, will serve as the interim CFO, while the company conducts a search.
Four trains currently being built
NextDecade is currently in the process of building a Liquified Natural Gas facility near Brownsville, TX. The company has its head office in downtown Houston.
Phase 1 involves the building of three liquefaction units (also called trains). Construction on Train 1 is about 25% complete. Construction on Train 2 has just started. Financing is in place for all of Phase 1 and 90% of the production capacity has been contracted with customers such as Shell, ExxonMobil and TotalEnergies. First production is expected in 2027.
Last month, the company gave the go-ahead (Final Investment decision) to Bechtel to start on Train 4. 77% of the production capacity has been contracted and the $6.68 billion cost will be funded through a mix of debt and equity. Train 5 is at a similar stage and the company plans to give the go-ahead on that train by the end of the year.
The company has also started the permitting process on Trains 6-8.
Interim CFO has plenty of LNG experience
Mr. Wahl joined the company in 2019 as Senior VP, Finance and was appointed CFO in February 2021. Prior to that, he was Head of Midstream Investment Banking for North America at Macquarie Capital. I am sure the financing of large datacenters increasingly resembles that of LNG projects, so it is not surprising that Mr. Wahl has been headhunted.
Mr. Mott joined the company in 2021as Senior VP, Corporate Strategy. He previously worked in the LNG business of the BG Group, before its acquisition by Shell.
Between 2014 and 2020, Mr. Mott was the CFO at Liquified Natural Gas Ltd, an Australian public company (with its management based in Houston) that was trying to develop an LNG facility in Lake Charles, Louisiana. The company sold its interests in the project in 2020.